Xcel Energy Files Colorado Least-Cost Resource Plan

04/30/2004

DENVER--(BUSINESS WIRE)--April 30, 2004--Xcel Energy today filed with the Colorado Public Utilities Commission its least-cost resource plan to develop and acquire 3,600 megawatts of electric generating capacity by 2013.

The plan, required by the commission every four years to cost effectively meet the state's growing energy needs, calls for a variety of new generating resources, including wind, natural gas and coal. The company analyzed more than 100 resource mix options, using a reasonable range of potential fuel costs and environmental regulations. Based on Xcel Energy forecasts, the company recommended a plan that includes:

    --  Up to 500 megawatts from renewable resources, predominantly
        wind power, acquired ahead of other needed resources

    --  An all-source bid process to secure new capacity from natural
        gas or other fossil fuel-fired generation, additional
        renewable energy resources, and demand reduction programs

    --  A proposed 750-megawatt coal-fired generating unit added to
        its Comanche Generating Station near Pueblo, Colo., of which
        Xcel Energy would own 500 megawatts.

Xcel Energy serves a Colorado electric customer base that grew by approximately 20 percent in the past 10 years, to reach more than 1.2 million in 2003. Individual customer demand for electricity grew by 13 percent during the same time period. Colorado customers now require up to 60 percent more electricity on peak demand days than they did just 10 years ago.

"Demand for electricity continues to rise in Colorado, both in terms of overall customer growth and per-customer requirements. Much of this demand drives the need for additional base-load generation -- resources that run virtually all of the time," said David Eves, vice president of Resource Acquisition and Planning for Xcel Energy. "Our plan offers the best mix of resources to help us serve that demand at reasonable prices."

Eighty percent of the proposed new generating capacity in the plan will be competitively bid. The requests for proposals would come in two phases. First, Xcel Energy asked for the commission's permission to request proposals for 500 megawatts of renewable energy resources -- predominantly wind power -- in July 2004. The request seeks to take advantage of the expected renewal of the federal production tax credit for wind energy in order to make the new renewable resources available by Dec. 2006.

In the second phase, Xcel Energy intends to re-negotiate contracts with existing power providers, and seek out new resources that can match customers' energy use. The company will also request proposals for additional resources, such as wind or solar, to further hedge against more volatile fossil-fuel prices. Xcel Energy will also seek bids for programs that lead to reductions in overall customer electricity demand. The company will evaluate all supply and demand-reduction options to develop the least-cost mix of resources.

To manage the risk of acquiring cost-effective base-load generating capacity through competitive bidding, Xcel Energy proposes to construct a new 750-megawatt, rate-based coal-fired generating unit at Pueblo's Comanche Generating Station. The $1.3 billion proposal calls for installing advanced emission control technology on the plant's new and existing units that will lead to an overall reduction in nitrogen oxide and sulfur dioxide emissions. The new unit would also employ technology to reduce its water use by approximately half of what a traditional wet-cooled unit would require each year. Xcel Energy's share of the project is estimated at $939 million.

Xcel Energy estimates that it will save customers between $200 million and $500 million in electricity rates over 30 years by using this facility rather than depending on other fuels for needed additional base-load capacity.

"We propose to more than double the output of Comanche Station, reduce the overall level of sulfur dioxide and nitrogen oxide emissions from the plant, make wise use of our state's valuable water resources, and save our customers money," said David Wilks, president of Energy Supply for Xcel Energy.

To proceed as quickly and cost effectively as possible, the company requested a waiver to the resource plan rule that limits the utility to owning no more than 250 megawatts in any single generating unit that is not competitively bid.

"With this waiver, we can expand the existing Comanche Generating Station more cost effectively and in a shorter period of time than it would take to build a similar facility at a new site," said Wilks.

The company will file an application on July 1, 2004, for commission approval of required transmission capacity from Comanche Station to a substation south of Denver. Additional transmission needs will be identified when the resource plan's competitive bidding process is complete.

To fund construction of the new Comanche unit, as well as purchased power obligations in the resource plan, the company's plan calls for increased equity investment to maintain acceptable credit ratings and borrowing costs. Xcel Energy therefore requested from the commission permission to recover these increased expenses through a rider to customer bills beginning January 1, 2005, and continuing until the unit goes into service. The rider is expected to be approximately $0.89 per month for the typical residential customer and $1.89 per month for the typical small business customer, averaged over the next five years. In addition, the company proposes to begin to recover construction work in progress when electric rates are reset in 2007, and remaining costs when the unit goes into service. Customer cost impacts for competitively bid resources will not be known until those resources are selected.

Xcel Energy (NYSE:XEL) is a major U.S. electricity and natural gas company with regulated operations in 11 Western and Midwestern states. Xcel Energy provides a comprehensive portfolio of energy-related products and services to 3.3 million electricity customers and 1.8 million natural gas customers through its regulated operating companies. In terms of customers, it is the fourth-largest combination natural gas and electricity company in the nation. Company headquarters are located in Minneapolis. More information is available at www.xcelenergy.com.

    CONTACT: Xcel Energy
             Media Relations, 303-294-2300
             www.xcelenergy.com