MINNEAPOLIS--(BUSINESS WIRE)--
Minnesota's largest wind farm and the state's largest transmission
line built to carry wind power into the Twin Cities were dedicated
today and will soon become fully operational, subject to final
approvals by the regional transmission operator.
A total of 137 wind turbines, with a maximum generating capacity
of 205 megawatts of electricity, comprise enXco's Fenton Wind Project
in southwestern Minnesota, making it the largest single wind farm in
the state.
"Today's event marks the 20th year in wind energy development for
our company," said James Walker, vice president of asset management
for enXco, "and to dedicate the state's largest wind park makes this
milestone even more special."
Xcel Energy's 345-kilovolt transmission line along with two major
115 kV lines will deliver the power into the Minnesota High voltage
transmission grid allowing delivery of the power from the Fenton Wind
farm and other wind power resources from the Buffalo Ridge region of
the state into the twin Cities area.
"This region of Minnesota is very rich in wind power resources and
we've been working hard to tap into it with this transmission line,"
said Doug Jaeger, vice president of transmission for Xcel Energy.
"Once the wind farms are fully developed in this region, we will be
able to deliver up to an 825 megawatt crop of wind power from the
fields of southwestern Minnesota to the Twin Cities market."
Under a 20-year agreement, enXco will own and operate the Fenton
Wind Park and sell all the energy it produces to Xcel Energy. The
agreement is similar to arrangements the independent power provider
has with the utility in its other service territories.
"We're proud to have built this magnificent wind farm not only
because it will provide alternative energy to the citizens of
Minnesota for years to come but also because it stands as a symbol of
this country's efforts to chart a new energy course," noted Tom
Wacker, senior vice president of Mortenson Construction, which built
the project for enXco. Wacker announced that Mortenson's Energy Group
celebrates its 50th completed wind farm project with Fenton.
Approximately 515 megawatts of wind power capacity has been
installed in the Buffalo Ridge area of southwestern Minnesota. About
350 megawatts of additional wind power capacity is planned to be
on-line by 2008. Existing transmission from the region was not able to
carry the anticipated wind power load until the new transmission lines
were completed. An additional leg of the 345-kilovolt transmission
line soon will be completed into Sioux Falls in order to support the
transmission grid in that region.
The transmission grid, in which the Fenton wind farm and
southwestern line will operate, is managed by the Midwest Independent
System Operator (MISO), one of the nation's regional transmission
management organizations. MISO is responsible for dispatching and
balancing generating and transmission resources to serve customer
demand throughout the Midwest and Upper Midwest region of the nation.
MISO is expected to commission the Fenton wind farm and transmission
lines into operation in the next few weeks.
During the 2007 legislative session, Minnesota lawmakers passed
and Gov. Tim Pawlenty signed into law legislation that requires the
state's utilities to obtain 25 percent of their electrical energy from
renewable resources. Xcel Energy, which supported the new law, must
obtain 30 percent of its electricity from renewables by 2020.
"That means we will have to build more wind farms and more
transmission in order to meet this ambitious goal," Jaeger said. "As
the nation's No. 1 wind power provider, and by working with companies
like enXco, as well as Burns & McDonnell and MYR Group, our two
largest contractors on our transmission upgrade project, we believe we
can do it."
Xcel Energy (NYSE:XEL) is a major U.S. electricity and natural gas
company with regulated operations in eight Western and Midwestern
states. Xcel Energy provides a comprehensive portfolio of
energy-related products and services to 3.3 million electricity
customers and 1.8 million natural gas customers through its regulated
operating companies. Company headquarters are located in Minneapolis.
More information is available at www.xcelenergy.com.
enXco, inc. (www.enxco.com) an EDF-EN Company (www.edf-en.com)
develops, constructs, operates and manages wind energy projects
throughout the United States. Since 1987 enXco has grown to be a
significant owner and developer of wind-energy projects. enXco is the
largest 3rd party provider for wind farms, with more than 3,600
turbines and more than 1,500 MW under contract.
Founded in 1954, Mortenson Construction is a U.S.-based,
family-owned construction company. As one of the nation's top
builders, Mortenson provides a complete range of services, including
planning, program management, preconstruction, general contracting,
construction management, design-build, and turn-key development.
Mortenson is the leading wind energy provider in North America.
Engineering News-Record ranked Mortenson 38 in the 2007 Top 400
Contractors listing and 17th Top Green Contractor. Mortenson recently
announced its purchase of renewable energy credits (RECs) from clean,
emission-free wind farms to power its U.S. offices which corresponds
to 100 percent of its electricity usage for its national headquarters
in Minneapolis and all six of its regional offices. Its innovative
approach to building structures and facilities for the advancement of
modern society is eloquently delivered through its commitment to
environmental and social stewardship. For more information, please
visit mortenson.com.
Source: Xcel Energy
Contact: Xcel Energy Media Relations, 612-215-5300
or
enXco Media Relations, 760-329-1437 extension 120
or
Mortenson Media Relations, 763-287-5151